Four of Eight Turbines Are Already Operating in Paks
At Hungary’s Paks nuclear power plant, four of eight turbines were again generating electricity on Sunday. Prime Minister Péter Magyar reported on the state of the work during weekend appearances from the power plant site and at a Sunday press conference in Paks, where Economy and Energy Minister István Kapitány and Defence Minister Romulusz Ruszin-Szendi also spoke. hnonline.sk ↗
Operations at the power plant had to be gradually restricted from the end of July because of the low water level of the Danube, until only one of the eight turbines remained in operation. According to available information, the third turbine was started on Saturday and the restart of the unit was broadcast live on a social network. During the night into Sunday, the plant’s third unit started running again, made possible by construction work and a rise in the Danube’s water level. teraz.sk ↗
The measures include the construction of a weir on the riverbed near Paks, intended to help ensure the safe operation of the power plant when water levels are low. According to government statements, construction is progressing faster than originally planned. Work was also carried out on other sections of the Hungarian part of the Danube. Telex ↗
Magyar also announced that after the work in Paks is completed, the government wants to submit legislation concerning water, energy and climate at extraordinary speed. Further developments will depend on the continuation of water-management interventions, the level of the Danube and the pace of restoring the power plant to full operation. HVG ↗
Operations at the power plant had to be gradually restricted from the end of July because of the low water level of the Danube, until only one of the eight turbines remained in operation. According to available information, the third turbine was started on Saturday and the restart of the unit was broadcast live on a social network. During the night into Sunday, the plant’s third unit started running again, made possible by construction work and a rise in the Danube’s water level. teraz.sk ↗
The measures include the construction of a weir on the riverbed near Paks, intended to help ensure the safe operation of the power plant when water levels are low. According to government statements, construction is progressing faster than originally planned. Work was also carried out on other sections of the Hungarian part of the Danube. Telex ↗
Magyar also announced that after the work in Paks is completed, the government wants to submit legislation concerning water, energy and climate at extraordinary speed. Further developments will depend on the continuation of water-management interventions, the level of the Danube and the pace of restoring the power plant to full operation. HVG ↗
This summary was generated by artificial intelligence. It may contain inaccuracies. Please verify information in the original sources below.
Sources (8)
Magyar Péter azt kéri a nagy cégektől, hogy szálljanak be az 56-os megemlékezésekbe
HVG
| 10:44 23.08.
Magyar Péter azt ígéri, a paksi munkák befejezése után példátlanul gyorsan nyújtanak be víz-, energia- és klímatörvényt
Telex
| 11:25 23.08.
Hiába építenek gátat és engednek plusz vizet a Dunába, augusztusban már aligha indul újra Románia atomerőműve
Telex
| 11:13 23.08.
Maďarský premiér: Už fungujú štyri z ôsmich turbín jadrovej elektrárne Paks
hnonline.sk
| 11:10 23.08.
Magyar: Už fungujú štyri z ôsmich turbín jadrovej elektrárne Paks
teraz.sk
| 10:38 23.08.
Gyorsabban épül a paksi fenékküszöb
Index.hu
| 09:40 23.08.
Érkeznek a friss bejelentések Magyar Pétertől, így áll most az építkezés Pakson - Élőben közvetíti a kormányfő a paksi munkálatok állását
Index.hu
| 09:22 23.08.
Élőben jelentkezik be Magyar Péter a paksi munkálatok helyszínéről
Index.hu
| 09:20 23.08.
🔥 You might also like
World
Hungary investigates negligence at Paks power plant. Ministers have one week to determine whether risks were reported to superiors
Budapest government ordered two extraordinary investigations into energy sector. It specifically asks whether it was warned about low Danube risks in previous y …
World
Bulgaria Reduced Nuclear Power for the First Time in 52 Years. The Danube near Bratislava No Longer Gives Water, but Takes It
Kozloduj reduced power for first time in 52 years. With Cernavoda and Paks, all three nuclear plants on Danube cut output. Near Bratislava, groundwater vanishin …
European Union
What Europe Is Writing About: Delegates Walked Out of Netanyahu's Speech, Vučić Announced the Time of His Resignation, Trump Hosted Xi Jinping
Dozens of delegations walked out of Netanyahu's UN speech, Vučić to resign Sunday evening, Trump hosted Xi Jinping at the White House. 37-country roundup.
© HotInfo
Geographic locations
From our newsroom original
All →
Pistorius questions Dobrindt's assessment of the violence in Germany

Director Michael Mann accidentally shoots himself in the leg in Los Angeles

Judge Dismisses Trump's Lawsuit Over Alaska Election

Mecca Pact Countries Held Their First Joint Talks in Tehran. They Agreed Only to Keep Talking

Cruise ship with over 3,300 people on board collided with two container ships in Bremerhaven

Swiss court convicts Belarusian over disappearance of Lukashenko opponent in 1999

Orbán for UN Secretary-General? WSJ Editorial Says Washington Is Pushing Him, Moscow Points to Latin America

International Criminal Court may use American software even under US sanctions